Oasis at Kearney Creek
  • Last Updated: September 07 2020
  • Pre-Construction Bid Date: None
  • Status: 90% contracts purchased

Suggested Pricing:

  • Project Contact Roles:    IN ORDER TO OBTAIN BID DOCUMENTS AND SUBMIT A BID, PLEASE CONTACT
    Contact Name Email Phone Role Emails sent Last date  
    RESTRICTED RESTRICTED RESTRICTED Other      
    RESTRICTED RESTRICTED RESTRICTED Project Manager      
  • Status/Contact Role Update:
    Update 1:
    Thanks for checking in but Doors  contract has already been let.
    Date: March 03 2020
    Update 2:
    Yes you can submit. Final cleaning will not take place until next Spring. Just send your quote to me
    
    D
    Date: July 06 2020
    Update 3: I already awarded the painting scope of work last year. Date: July 16 2020
    Update 4: This work is not needed until March of 2021. Also need to add cleaning all windows inside and out on it. Date: August 27 2020
    Update 5: None Date: None


  • Description:
    • PROJECTS: We broke ground at a new development at Kearney Creek; exciting things are underway! The Oasis at Kearney Creek will be a new community 96 units of affordable housing for seniors 55+.


General Contractor Information:

  • Name: RESTRICTED
  • Address: RESTRICTED
  • GC Phone: RESTRICTED
  • GC Website: RESTRICTED
  • GC Vendor Qualification Application: RESTRICTED
  • GC LinkedIn: RESTRICTED
  • GC Facebook: RESTRICTED
  • GC Twitter: RESTRICTED