La Terra Santa Monica
  • Last Updated: August 22 2020
  • Pre-Construction Bid Date: None
  • Status: Work in progress

Suggested Pricing:

  • Project Contact Roles:    IN ORDER TO OBTAIN BID DOCUMENTS AND SUBMIT A BID, PLEASE CONTACT
    Contact Name Email Phone Role Emails sent Last date  
    RESTRICTED RESTRICTED RESTRICTED Project engineer      
    RESTRICTED RESTRICTED RESTRICTED Other      
    RESTRICTED RESTRICTED RESTRICTED Project Manager      
  • Status/Contact Role Update:
    Update 1:
    We have only broken ground.  Substantial completion is March 2021
    
    JP
    Date: March 18 2020
    Update 2:
    The projects are already underway and we have concreted subbed out.
    Date: August 20 2020
    Update 3: I am not involved with this project, Doug Beckman is the project manager, I have copied Doug on this e-mail. Date: January 27 2020
    Update 4: So here are some projects that we are awarded. Please provide a hard number: La Terra Santa Monica Projects: Date: June 19 2019
    Update 5: I’m the PE on the Santa Monica projects (Cloverfield/Broadway and Yale). We are presently in the buyout phase for all trades. Shoring and excavation are underway. Anticipated substantial completion of the projects is March 2021. Feel free to contact me if you have any further questions. Date: March 13 2020


  • Description:
    • http://laterradev.com/projects/santa-monica-cloverfield/
      Two new projects in Santa Monica in walking distance from the Expo Line, both designed by Tighe Architecture, are expected to open in 2020.
      Developed by LaTerra Development, both projects will feature apartments.
      Construction has already begun on one project at Broadway and Cloverfield. The two-building complex will hold 49 total apartments, five of them affordable, and nearly 11,000 square feet of ground floor retail, all a half-mile from the Expo Line’s 26th Street/Bergamot station.
      Within the next two months, LaTerra plans to break ground on a separate project nearby. Located at Santa Monica and Yale, the development will hold 46 market-rate and four affordable apartments, plus 10,000 square feet of retail space—about three-quarters of a mile from the 26th Street station.
      Both apartment projects will have rooftop decks and amenities including gyms, pet-focused amenities, and outdoor lounge areas. They’ll each offer a mix of studios, one-, two-, and three-bedroom units, a choice that was “crafted carefully to appeal to Santa Monica’s wide resident demographic ranging from Silicon Beach professionals to entertainment industry creatives to hip entrepreneurs,” La Terra says in an announcement for the project.
      
      Both are expected to open relatively soon, in the second half of 2020.


General Contractor Information:

  • Name: RESTRICTED
  • Address: RESTRICTED
  • GC Phone: RESTRICTED
  • GC Website: RESTRICTED
  • GC Vendor Qualification Application: RESTRICTED
  • GC LinkedIn: RESTRICTED
  • GC Facebook: RESTRICTED
  • GC Twitter: RESTRICTED