BJ's Wholesale Club Seabrook
  • Street: RESTRICTED
  • City/State: Seabrook, New Hampshire
  • Sq Ft: 90,000
  • Number of rooms/Units: None
  • Building Type: Industrial
  • Plans/Drawings: RESTRICTED
  • Last Updated: September 14 2020
  • Pre-Construction Bid Date: March 05 2020
  • Status: Pre-construction

Suggested Pricing:

  • Project Contact Roles:    IN ORDER TO OBTAIN BID DOCUMENTS AND SUBMIT A BID, PLEASE CONTACT
    Contact Name Email Phone Role Emails sent Last date  
    RESTRICTED RESTRICTED RESTRICTED Project Manager      
    RESTRICTED RESTRICTED RESTRICTED Estimating      
    RESTRICTED RESTRICTED RESTRICTED Estimating      
  • Status/Contact Role Update:
    Update 1:
    CONSTRUCTION START HAS NOT HAPPENED YET
    Date: June 16 2020
    Update 2:
    this project has been awarded for painting.
    Date: July 16 2020
    Update 3: None Date: None
    Update 4: None Date: None
    Update 5: None Date: None


  • Description:
    • In an unconventional move, the town’s Planning Board “conditionally approved” a new shopping center that may bring a 90,000-square-foot BJ’s Wholesale Club and 200-seat restaurant to the busy Route 1 retail strip in town.
      
      The project consists of the construction of a new BJ’s Wholesale Club, and MINOR site work as indicated on the drawings.  THE WORK INCLUDES BUT IS NOT LIMITED TO: Partial and Minor Sitework (See NOTES below), Foundations, Slabs, Structural Concrete, 12” Precast Concrete Panels (By BJ’s), Concrete Ready-Mix, Rebar and mesh, Polished concrete (By BJ’s), Masonry, Structural Steel, Ornamental Metals, Metal Stairs, Millwork, Carpentry, Thermoplastic Membrane Roofing, EIFS, Vinyl Siding, Building Insulation, Roof Accessories, Skylights, Fire Resistive Joint Systems, Joint Sealants, Doors & Hardware, Overhead Coiling Doors, Overhead Sectional Doors, Aluminum Entrances and Storefronts, Aluminum Windows, Automatic Entrance Doors, Metal Stud & Drywall, Acoustical Ceilings, Ceramic Tile, Resilient Floor Tile, Carpeting, Painting, Overhead-Supported Canopies, Specialties, Toilet Compartments and Toilet Accessories, Loading Dock Equipment, Wheelchair lifts, Fixture and Equipment Installation, Fire Protection, Plumbing, HVAC and Electrical (including Fire Alarm).
      
      NOTES:
      1.      OPEN SHOP
      2.      If NH is not your region or you are not licensed in this state, please just click “Not Bidding” and no need to email me directly on this issue.
      3.      Projected Construction Start: 4-16-20
      4.      Projected Construction Completion: 10-2-20
      5.      This is a pad ready site and the sitework is limited to:
      a.      Excavation and Backfill for interior building utilities.
      b.      Excavation for Freezers.
      c.      Utility connections to 5’ outside the walls.
      d.      All sidewalk and pad prep by others.
      e.      Remainder of sitework by others.
      6.      The Following items are by BJ’s:
      a.      Precast Panels (erected after steel erection)
      b.      Floor Polish
      c.      Refrigeration
      d.      Supply of CPI Panel, Generator set, RTU’s.
      7.      Fixture Installation includes:
      a.      Unloading the racks and bringing them inside for installation by others.
      b.      Unload and place Refrigerated Cases


General Contractor Information:

  • Name: RESTRICTED
  • Address: RESTRICTED
  • GC Phone: RESTRICTED
  • GC Website: RESTRICTED
  • GC Vendor Qualification Application: RESTRICTED
  • GC LinkedIn: RESTRICTED
  • GC Facebook: RESTRICTED
  • GC Twitter: RESTRICTED