Midland project

  • Street: RESTRICTED
  • City/State: Tulsa, Oklahoma
  • Sq Ft: 46,000
  • Number of rooms/Units: None
  • Project Type: None
  • Plans/Drawings: RESTRICTED
  • Last Updated: April 11 2020
  • Pre-Construction Bid Date: None
  • Status: Project in progress-GC awarded

Suggested Pricing:

  • Project Contact Roles:    IN ORDER TO OBTAIN BID DOCUMENTS AND SUBMIT A BID, PLEASE CONTACT
    Contact Name Email Phone Role
    RESTRICTED RESTRICTED RESTRICTED Project Manager  
  • Status/Contact Role Update:
    Update 1:
    None
    Date: None
    Update 2:
    None
    Date: None
    Update 3: None Date: None
    Update 4: None Date: None
    Update 5: None Date: None


  • Description:
    • The team is continuing to make progress on our Midland project in downtown Tulsa. The slab in one section of the building was uneven throughout and had multiple sunken areas, resulting in the need for a new topping slab. This presented the opportunity to remove the existing slab to create space for new power to be installed in the floor. 
      Currently, the slab has been demolished and we have started the process of bringing in fill material, installing the power, and placing the topping slab.
      
      The architect for the project, which will revamp between 40,000-46,000 square feet of space, is Mass Architects, which has offices in Tulsa and Oklahoma City. Duane Mass is the designer behind the renovation of the state Capitol.


General Contractor Information:

  • Name: RESTRICTED
  • Address: RESTRICTED