Georgia Power canton ops hq

  • Street: RESTRICTED
  • City/State: Canton, Georgia
  • Sq Ft: 16,718
  • Number of rooms/Units: None
  • Project Type: None
  • Plans/Drawings: RESTRICTED
  • Last Updated: May 15 2020
  • Pre-Construction Bid Date: None
  • Status: Project in progress-GC awarded

Suggested Pricing:

  • Project Contact Roles:    IN ORDER TO OBTAIN BID DOCUMENTS AND SUBMIT A BID, PLEASE CONTACT
    Contact Name Email Phone Role
    RESTRICTED RESTRICTED RESTRICTED Other  
    RESTRICTED RESTRICTED RESTRICTED Other  
    RESTRICTED RESTRICTED RESTRICTED Other  
  • Status/Contact Role Update:
    Update 1:
    If you have immediate questions, please contact the following people:
     
     · Georgia Power - Sam Beale
     
    Ryan Shanteau
    Date: November 27 2019
    Update 2:
    We have not yet purchased the carpentry, currently focused on the ‘early’ trades – site, concrete, steel, etc.
    
    What is the current lead time for: shop drawings, and casework delivery once approved shop drawings are received.
    
    
    Sam Beale
    Date: December 27 2019
    Update 3: It will be 6 months before we have buildings that can be visited. Super Date: April 01 2020
    Update 4: expect to award the cleaning work in a month or two after we get all of the other subcontracts awarded. Sam Project Manage January 21, 2020 at 8:54 AM Date: January 21 2020
    Update 5: We are still grading for the building pads, so not much to see from a Doors/Frames/Hardware perspective. Date: March 03 2020


  • Description:
    • None


General Contractor Information:

  • Name: RESTRICTED
  • Address: RESTRICTED
  • GC Phone: RESTRICTED
  • GC Website: RESTRICTED
  • GC Vendor Qualification Application: RESTRICTED
  • GC LinkedIn: RESTRICTED
  • GC Facebook: RESTRICTED
  • GC Twitter: RESTRICTED